E Connect e - o X * G : F C 0 https://newconnect.mheducation.com/flow/connect.html # Apps P Haiku & Drive Check my work mode: This shows what is correct or incorrect for the work you have completed so far. It does not indicate completion. Return to question Exercise 10-7 Direct Materials Variances (LO10-1] Huron Company produces a commercial cleaning compound known as Zoom. The direct materials and direct labor standards for one unit of Zoom are given below: points Standard Quantity or Standard Price Hours or Rate 4.6 pounds $ 2.50 per pound 0.2 hours $18.00 per hour Standard Cost $11.58 $ 2.40 Direct materials Direct lobor During the most recent month, the following activity was recorded. a. Twenty thousand pounds of material were purchased at a cost of $2.35 per pound. b. The company produced only 3,000 units, using 14,750 pounds of material. (The rest of the material purchased remained in raw materials inventory.) c. 750 hours of direct labor time were recorded at a total labor cost of $14,925. Required: Compute the materials price and quantity variances for the month. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) & Answer is complete but not entirely correct. Graw 3:34 PM 0 O Type here to search o 9 wi A A A A D & ilk 3/11/2018 YExplanation / Answer
Compute variance :
Material price variance = (2.50-2.35)*20000 = 3000 F
Material quantity variance = (3000*4.6-14750)*2.50 = 2375 U
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.