Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Selected accounts with some amounts omitted are as follows Work in Process Aug.

ID: 341848 • Letter: S

Question

Selected accounts with some amounts omitted are as follows Work in Process Aug. 1 Balance 268,000 Aug. 31 Gods finished 125,400 31 Direct materials 31 Direct labor 45,600 1 Factory overhead Factory Overhead Aug. 1- 31 Costs incurred 109,800 Aug. 1 Balance 31 Applied 14,900 If the balance of Work in Process at August 31 is $209,200, what was the amount debited to Work in Process for factory overhead in August, assuming a factory overhead rate of 30% of direct labor costs? $109,800 $125,400 $13,680 $14,900

Explanation / Answer

Amount debited to Work in Process for Factory overhead = 45600*30%= $13680 Option 3 is correct

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote