Question 3 of 50 The work breakdown structure (WBS) provides a foundation for th
ID: 340220 • Letter: Q
Question
Question 3 of 50 The work breakdown structure (WBS) provides a foundation for the project to later develop a responsibility assignment matrix (RAM) and to allocate resources. Which of the following statements about a WBS is false? O It is used to build a project schedule O It is a key project-planning tool O It is a hierarchical representation of deliverables. O With each lower level it breaks a project into greater detail. Question 4 of 50 You are a project manager in a Engineering company and manage a team of 20 people in a virtual project team across multiple time zones. There were concerns that team members would not be able to work well in this virtual team structure. However, you are mid-way into the project and team members have successfully figured out efficient ways to work together effectively. The team is in which stage of group development? O Forming O Smoothing O Norming O Performing Question 5 of 50 Assuming a PERT weighted average computation, what is the probability of completing the project within plus or minus 3 standard deviations of the mean? o 99.999% ? 99.73% ? 99.00% O 95.46%Explanation / Answer
3)
WBS is work breakdown structure in which each work package is decomposed into the activities required to produce the work package deliverables. It is not a planning tool
Answer B : It is a key project -planning tool
4) There are five stages of group development through which project team undergoes :
In the question , team has started working effectively and efficiently so they are in Performing stage .
Answer D : Performing
5)
Within plus or minus 3 sigma , probability is 99.73%
Answer B: 99.73%
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.