PROBLEM 1. True or False Questions. a) A queue will not form if the service capa

ID: 339732 • Letter: P

Question

PROBLEM 1. True or False Questions. a) A queue will not form if the service capacity is higher than the demand rate. True False
b) Using an appointment system increases the capacity of a system. True False
c) Suppose there is a set of jobs to be processed at a resource. Shortest Processing Time always sequences the jobs in a different order than First Come First Serve. True False
d) Crashing an activity always shorten the completion time of a project. True False PROBLEM 1. True or False Questions. a) A queue will not form if the service capacity is higher than the demand rate. True False
b) Using an appointment system increases the capacity of a system. True False
c) Suppose there is a set of jobs to be processed at a resource. Shortest Processing Time always sequences the jobs in a different order than First Come First Serve. True False
d) Crashing an activity always shorten the completion time of a project. True False PROBLEM 1. True or False Questions. a) A queue will not form if the service capacity is higher than the demand rate. True False
b) Using an appointment system increases the capacity of a system. True False
c) Suppose there is a set of jobs to be processed at a resource. Shortest Processing Time always sequences the jobs in a different order than First Come First Serve. True False
d) Crashing an activity always shorten the completion time of a project. True False

Explanation / Answer

A) True:

If the service capacity is higher than the demand rate than a queue will not be formed.

B) True

With the help of an appointment system increase the capacity of a system because there is no chance of clash between two process of activities. So it is the main reason that the appointment system increase the capacity of a system.

C) True

Shortest processing time always sequences the jobs in different order than FCFS. Because in SPT there is number of jobs and they are scheduled according to their process timings. It means those job who has less processing time is processed first and vice versa.

D) True

When an activity is crashed than the completion time will be reduced.