1. If a local government implements a program as designed, but the program did not produce the desired results, this would be termed or classified as _______________________ failure.

2. A policy is implemented in order to solve the problem of malnutrition. The extent to which we can unequivocally conclude that it was the policy that solved the malnutrition problem is called ____________________.

3. The process of selecting clients who need little help in order to report more successes of programs is called

A) Implementation B) Testing             C) Creaming

D) generalizing E) reliability          F) validity

Explanation / Answer

1: Implementation faillure

The program was designed as per the requirements but were not able to execute

2:acceptance level

In this stage the project or plan which was implemented hit the target to an extent.

3: Reliability

This offered selection of client who has prior success records on the same line on contractual business