Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Which of the following statements is correct regarding the use of an MRP system?

ID: 338601 • Letter: W

Question

Which of the following statements is correct regarding the use of an MRP system?

D. All of the above are correct

The master production schedule for two products, A and B, is shown below.

To manufacture item A, four (4) units of component C are required. To manufacture item B, two (2) units of component C are required. There are 10 units of component B on hand currently. Using this information, determine the gross requirements for component C to start week 1.

A. Many firms have insisted their suppliers also install MRP systems B. MRP has essentially eliminated the need for engineering change order systems C. With MRP, all component, part, and raw material inventories are managed with order-point systems

D. All of the above are correct

The master production schedule for two products, A and B, is shown below.

Master Production Schedule
Week 1 Product A 30 Product B 35

To manufacture item A, four (4) units of component C are required. To manufacture item B, two (2) units of component C are required. There are 10 units of component B on hand currently. Using this information, determine the gross requirements for component C to start week 1.

A. 65 B. 170 C. 190 D. 200 E. None of the above

Explanation / Answer

Which of the following statements is correct regarding the use of an MRP system?

D. All of the above are correct

The master production schedule for two products, A and B, is shown below.

To manufacture item A, four (4) units of component C are required. To manufacture item B, two (2) units of component C are required. There are 10 units of component B on hand currently. Using this information, determine the gross requirements for component C to start week 1.

A. Many firms have insisted their suppliers also install MRP systems B. MRP has essentially eliminated the need for engineering change order systems C. With MRP, all component, part, and raw material inventories are managed with order-point systems

D. All of the above are correct

The master production schedule for two products, A and B, is shown below.

Master Production Schedule
Week 1 Product A 30 Product B 35

To manufacture item A, four (4) units of component C are required. To manufacture item B, two (2) units of component C are required. There are 10 units of component B on hand currently. Using this information, determine the gross requirements for component C to start week 1.

A. 65 B. 170 C. 190 D. 200 E. None of the above
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote