Which of the following statements is correct regarding the use of an MRP system?
ID: 338601 • Letter: W
Question
Which of the following statements is correct regarding the use of an MRP system?
D. All of the above are correct
The master production schedule for two products, A and B, is shown below.
To manufacture item A, four (4) units of component C are required. To manufacture item B, two (2) units of component C are required. There are 10 units of component B on hand currently. Using this information, determine the gross requirements for component C to start week 1.
A. Many firms have insisted their suppliers also install MRP systems B. MRP has essentially eliminated the need for engineering change order systems C. With MRP, all component, part, and raw material inventories are managed with order-point systemsD. All of the above are correct
The master production schedule for two products, A and B, is shown below.
Master Production ScheduleWeek 1 Product A 30 Product B 35
To manufacture item A, four (4) units of component C are required. To manufacture item B, two (2) units of component C are required. There are 10 units of component B on hand currently. Using this information, determine the gross requirements for component C to start week 1.
A. 65 B. 170 C. 190 D. 200 E. None of the aboveExplanation / Answer
Which of the following statements is correct regarding the use of an MRP system?
D. All of the above are correct
The master production schedule for two products, A and B, is shown below.
To manufacture item A, four (4) units of component C are required. To manufacture item B, two (2) units of component C are required. There are 10 units of component B on hand currently. Using this information, determine the gross requirements for component C to start week 1.
A. Many firms have insisted their suppliers also install MRP systems B. MRP has essentially eliminated the need for engineering change order systems C. With MRP, all component, part, and raw material inventories are managed with order-point systemsD. All of the above are correct
The master production schedule for two products, A and B, is shown below.
Master Production ScheduleWeek 1 Product A 30 Product B 35
To manufacture item A, four (4) units of component C are required. To manufacture item B, two (2) units of component C are required. There are 10 units of component B on hand currently. Using this information, determine the gross requirements for component C to start week 1.
A. 65 B. 170 C. 190 D. 200 E. None of the aboveRelated Questions