Your project to obtain charitable donations is now 46 days into a planned 56-day
ID: 336760 • Letter: Y
Question
Your project to obtain charitable donations is now 46 days into a planned 56-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 40 days of the project and to bring in $24,800. Even though we are 46 days into the project, we still see that we have only 92% of this activity complete. The second activity relates to company donations and is scheduled to run for 46 days starting on day 6 and extending through day 52. We estimate that even though we should have (40/46) 87% of this activity complete, it is actually only 50% complete. This part of the project was scheduled to bring in $149,800 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $49,600. So far $175,000 has actually been brought in on the project.
Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to 3 decimal places.)
rev: 08_07_2014_QC_522
Schedule variance $ Schedule performance index Cost variance $ Cost performance indexExplanation / Answer
At 46 days
Task 1
Planned Completion = 100%
Actual Completion = 92%
Planned Value = 24800
Earned value = 92%*24800 = 22816
Task2
Planned Completion = 40/46 = 87%
Actual completion = 50%
Budget amount = 149800
Planned Value = 87%*149800 = 130326
Earned value = 50%*149800 = 74900
Task 3
Start date = 42 Complete date = 52
Planned Completion = 4/10 = 40%
Actual completion = 0%
Budget = 49600
Planned value = 40%*49600 = 19840
Earned value = 0%*49600 = 0
Overall Project level
Planned value,PV = sum of all three task planned value = 24800 + 130326 + 19840 = 174966
Earned value,EV = sum of all three task earned value =22816 +74900 + 0 = 97716
Actual Cost ,AC = 175000
Schedule variance = EV-PV = 97716- 174966 = -77250
Schedule Performance Index, SPI = EV/PV = 97716/174966 = 0.558
Cost Variance = EV-AC = 97716-175000 = -77284
Cost Performance Index = EV/AC = 97716/ 175000 = 0.558