Activit 36 41 1051 21 1 15 6 10 36 46 51 16 521 26 10 51 51 1110 21 1. How many
ID: 336225 • Letter: A
Question
Activit 36 41 1051 21 1 15 6 10 36 46 51 16 521 26 10 51 51 1110 21 1. How many Working Days does our schedule take to complete? 2. Assuming we don't work on weekends, if this project starts on February 5, 2018, what day will it finish on? 3. How many Calendar Days will this project take to complete? 4. If the subcontractor doing Task F takes 18 days to complete its task, how many Float Days remain for the subcontractor doing Task I? 5. If Task H takes an additional 5 days to complete, how many Working Days will our project take to complete? 6. If Task G can be shortened to 5 days, how many Working Days will our project take to complete? 7. If Change Order - 01 is placed between Task F and Task I and its Duration is 10 days, how many days will be added to the total duration of our Project? Change Order- 02 is placed between Task H and Task K and its Duration is 10 days, how many days will be added to the total duration of our Project? Change Order-03 eliminates Task C. How many days will be added to the total duration of our Project?Explanation / Answer
1. Activity L gets finished on day 56. So total working days= 56 days
2. Project starts on Feb 5, 2018. Project will get finished on April 23, 2018
3. Calendar days =78 days
4. Task I has 7 days to finish as Task F takes its 3 days
5. Task H is not on the critical path, Its duration will not affect the project duration.
6. Task G is a critical activity. if it gets shortened by 5 days, the project will finish 5 days earlier i.e. 50 days.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.