2. Which of the following assignments of tasks to workstations will not produce 125 mystifiers in a 40-hour week?

a) ABF, CD, GEHI, JK
b) ABE, CD, FGH, IJK
c) ACD, BFE, GHI, JK
d) ABC, DFG, EHI, JK

3. Of the feasible assembly lines given here, which line will produce the highest output?

a) ABF, CD, GEHI, JK
b) ABE, CD, FGH, IJK
c) ACD, BFE, GHI, JK
d) ABC, DFG, EHI, JK

4. What is the actual cycle time of the line chosen above?

5. What is the actual output in a 40-hr week?

6. What is the efficiency of the line?

Please explain how you get to each answer. Thank you!

The precedence diagram and task times (in minutes) for assembling McCauley's Mystifier are shown here. Set up an assembly line to produce 125 mystifiers in a 40-hour week. 8 5 4 10 0

Explanation / Answer

2 ans) a) ABF, CD, GEHI, JK

3 ans) b) ABE, CD, FGH, IJK

4 ans) desired cycle time = (40*60)/125 =19.2 min

so actual cycle time = 19

6 ana) efficency = 61/4*19 =0.8026 =80%

Hire Me For All Your Tutoring Needs