Question 1 of 21
Question 2 of 21
Question 3 of 21
Question 4 of 21
Question 5 of 21
Question 6 of 21
Question 7 of 21
Question 1 of 21
A Forward pass is required while computing the early start and early finish times of activities. A. True B. False Reset SelectionQuestion 2 of 21
CPM network scheduling assumes a second order (non-linear) time-cost tradeoff exists. A. True B. False Reset SelectionQuestion 3 of 21
The early start and late start times are equal along the critical path of a network. A. True B. False Reset SelectionQuestion 4 of 21
Network scheduling methods allow precise determination of the critical path, whereas Gantt charts cannot be used to determine the critical path. True False Reset SelectionQuestion 5 of 21
The job of the project manager is to: A. Control all costs B. Control schedule, and performance of the project C. Keep within the budget, no matter what D. All of the above Reset SelectionQuestion 6 of 21
Project management requires A. scheduling, planning, and controlling B. analytic skills C. behavioral skills D. All of the above Reset SelectionQuestion 7 of 21
Multiple critical paths can exist under CPM because: A. There is more than one way to complete the project B. Different network paths exist, each with the same total time C. Great flexibility of activity sequences is available D. None of the aboveExplanation / Answer
1. (A) True
2. (B) False
3. (A) True
4. (A) True
5. (D). All of the above
6. (D). All of the above
7. (B). Different network paths can have the same total time
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.