Suppose that you are the assigning costs to a major project to be undertaken thi
ID: 3329079 • Letter: S
Question
Suppose that you are the assigning costs to a major project to be undertaken this year by your firm, University Applications. One particular coding process involves many labor-hours, but highly redundant work. You anticipate a total of 200,000 labor-hours to complete the first iteration of the coding and a learning curve rate of 70%. You are attempting to estimate the cost of the twentieth iteration of this coding sequence.
Based on this information and a $60 per hour labor rate, what would you expect to budget as
A. The cost of the twentieth iteration?
B. The cost of the fortieth iteration?
Explanation / Answer
Solution:
Learning curve rate = log (0.7) / log (2) = -0.515
Time to complete 20th iteration = 200,000 x [20 ^ (-0.515)] = 42756 labor hours
Time to complete 40th iteration = 200,000 x [40 ^ (-0.515)] = 29920 labor hours
Cost of complete 20th iteration = 42756 x $60 = $2,565,360.00
Cost of complete 40th iteration = 29920 x $60 = $1,795,200.00