firm trains operators to do certain tasks on a production line. Those operators
ID: 3322739 • Letter: F
Question
firm trains operators to do certain tasks on a production line. Those operators wheo (6l end the training course are known to be able to meet their production quotas 90% of the time. Operators who do not take the training co time. Fifty percent of operators attend the course. (a) What is the probability that an operator meets her/his production quota? (b) Given that an operator meets his/her production quota, what is the probability t urse only meet their guotas 60% of the he/she attended the course? (6 pointsExplanation / Answer
P(Trained operators meet quota) = .90
P(untrained operators meet quota) = .60
P(Training) = 0.5.
a)
P(Operator meets quota) = P(Training)* P(Trained operators meet quota) + P(no Training)* P(untrained operators meet quota)
= 0.5 * 0.90 + (1-0.5) * 0.60
= 0.45+0.30
= 0.75
b)
P(Training/Operator meets quota) =
P(Trained operators meet quota) / [P(Trained operators meet quota)+ P(unTrained operators meet quota)]
= 0.90 / (0.90+0.60)
= 0.90/1.5
= 0.60