NYIT NEW YORK INSTITUTE oF TECHNOLOGY Semester Fall 2017 Class: Eng 251 Class Name: Project Engineering Class Text Operations Management, 11th edition Instructor Jay Quiz Number 1 Covering: Chapters 1, 2, 3, and 4 Your Name Section 1: 25 points each question, long answers with calculations involved. You can get partial credit for each question. You must show the calculations involved. You may either use an excel spreadsheet for your answers, or you may perfom them with a calculator in the space below. (A) Homewood Circuit Boards Inc made 24,500 printed circuit boards in September, consuming the following resources: Labor: 6,200 hours at $16.00 per hour Raw Material: 1,800 pounds of solder at $15 per pound Electricity: 46,000 kilowatt-hours of electricity at $.11 per kilowatt-hour What is the labor productivity per hour for these circuit boards at Homewood? What is the multifactor productivity for these circuit boards at Homewood? Answer BoxExplanation / Answer
a) Labor productivity per hour= 24500/6200=3.95
b) Multifactor productivity= 24500/{(6200*16)+ (1800*15)+ (46000*11)}= 24500/99200+27000+506000= 24500/632200= 0.03875356
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.