Statistical quality control question C5. Consider a control chart design using 3
ID: 3305258 • Letter: S
Question
Statistical quality control question
C5. Consider a control chart design using 3 sigma control limits, n-10, and h- 20 minutes, which the statements are true? (Multiple answers may be possible.) ARL-average run length and ATS-average time to signal. If you are not sure about your answers, please list your formulations in the questions. Refer it as C5 When there is a 1.5 sigma shift, ATS-21 minutes When the process is in control, ATS is 123 hours. When there is a 1.5 sigma shift, ARL-1.05 When the process is in control, ATS is 370 hoursExplanation / Answer
ARL = 1/p = 1/0.0027 = 370 p is 0.0027 under 3 sigma limit.
ATS = ARL*h = 370*1/3 hours = 123 hours {20 min = 1/3 hours}
option B) is correct
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.