AE Manufacturing has 60 machine hours every day. AE Manufacturing two products,

ID: 329347 • Letter: A

Question

AE Manufacturing has 60 machine hours every day. AE Manufacturing two products, A and B. When changing over from producing product B to A, there is no change over time. When changing over from producing product A to B, it takes 8 machine hours. If the previous day ended with producing product B, what is the effective capacity when AE Manufacturing has the following schedule: product A, product B, product A.

56 machine hours per day

60 machine hours per day

44 machine hours per day

52 machine hours per day

56 machine hours per day

60 machine hours per day

44 machine hours per day

52 machine hours per day

Explanation / Answer

Given values:

Design capacity = 60 machine hours per day

Time taken from product B to A = 0 machine hours

Time taken from product A to B = 8 machine hours

Production schedule = A — B — A

Solution:

Previous day ended with Product B. Since, there is 0 changing over time from B to A, the new day will immediately begin with producing product A.

Beginning = Product A, changeover time = 0

Product A to B, changeover time = 8 machine hours

Product B to A, changeover time = 0 machine hours

Effective capacity = Design capacity — Total Change over time

Effective capacity = 60 — (0 + 8 + 0) = 52

Effective capacity = 52 machine hours per day