A project has four activities (A, B, C, and D) that must be performed sequential
ID: 3277941 • Letter: A
Question
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
Use the random numbers 0.1778, 0.9617, 0.6849 and 0.4503 to simulate the completion time of the project in weeks.
Discuss how simulation could be used to estimate the probability that the project can be completed in 35 weeks or less.
Simulation provides a distribution of project completion times. The ___mean-or-percent______ of times 35 weeks and under can be used to estimate the probability that the project will be completed within 35 weeks.
Activity Activity Time
(weeks)
Probability A 5 0.25 6 0.35 7 0.25 8 0.15 B 3 0.20 5 0.55 7 0.25 C 10 0.10 12 0.25 14 0.40 16 0.20 18 0.05 D 8 0.60 10 0.40
Explanation / Answer
The base-case, worst-case, and best-case calculations for the time to complete the project is,
The random numbers 0.1778, 0.9617, 0.6849 and 0.4503 to simulate the completion time of the project in weeks are given by,
Simulation provides a distribution of project completion times. The mean-or-percent complition of times 35 weeks and under can be used to estimate the probability that the project will be completed within 35 weeks.
Activity Base case Worst case Best case A 6 weeks 8 weeks 5 weeks B 5 weeks 7 weeks 3 weeks C 14 weeks 18 weeks 10 weeks D 8 weeks 10 weeks 8 weeks Total 33 weeks 43 weeks 26 weeksRelated Questions