Secure https://www.mathd tudent/PlayerHomework.aspx?homeworkld 440181402&questionld-; 12&flushed; false&cld; 4608095&review; yes&centerwin; yes OMG 322-30 Fall 2017 Myke De R ma Review Homework: Chapter 3 Score: 0.22 of 1 pt 120f 17 Hw Score: 74.44%, 14.89 of Problem 3.8b Question Help Activity Immediate Predecessor(s) Time (days) 10 A, D E,F 12 - This exercise contains only parts b, c, and d b) The critical activities for the leadership training program development project are B D-E-G c) The project length for the leadership training program development project 30 days. d) Slack time for each of the activities is Activity Slack Time Question is complete. Tap on the red indicators to see incorrect answers.

Explanation / Answer

The slack time is calculated as:

Slack Time = LS-ES

Activity Time ES EF LS LF Slack A 4 0 4 11 15 11 B 5 0 5 0 5 0 C 2 0 2 11 13 11 D 10 5 15 5 15 0 E 3 15 18 15 18 0 F 5 2 7 13 18 11 G 12 18 30 18 30 0
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote