Northwest University is in the process of completing a computer bus network that will connect computer facilities throughout the university. The prime objective is to string a main cable from one end of the campus to the other (nodes 1-25) though underground conduits. These conduits are shown in the network; the distance between them is in hundreds of feet. Fortunately, these underground conduits have remaining capacity through which the bus cabel can be placed.

The model consists of how many jobs?

14

11

6

10

3

4

2. The solution to the problem is $75.5?

T/F

3. In order to solve the problem which would be the best quantitative method to use?

multi-criteria decision making

transportation model

assignment model

network flow model

transshipment model

critical path network

10 12 17 14 15 16 19 20 To 10 21 23

Explanation / Answer

1) Since the problem can be divided into 7 stages the number jobs is equal to 7

2) The solution of the problem is $75.5. Hence the statement is False ( The optimum solution is $49 and the optimum path is 1-3-7-12-16-20-23-25)

3) The best quantitatie method to solve the problem is the Multi-Criteria Decision Making