Tullis Construction enters into a long-term fixed price contract to build an off
ID: 3199682 • Letter: T
Question
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year. 20. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of Year 1 on the balance sheet assuming the use of the percentage-of-completion method? A. liability of $250,000 B. liability of $4,000,000 C. asset of $0 D. asset of $3,000,000 Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year. 20. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of Year 1 on the balance sheet assuming the use of the percentage-of-completion method? A. liability of $250,000 B. liability of $4,000,000 C. asset of $0 D. asset of $3,000,000Explanation / Answer
= 3/8 * 100% = 37.5 %
Revenue recognised = 37.5% of $10,000,000 = $ 3750000
Revenue earned = $ 4000000
Hence, liability = $ 4000000 - $ 375000 = $ 250,000
Option A
Percentage of Work Completed = Expenditures Incurred from Inception to Date / Total Estimated Costs for the ContractRelated Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.