QUESTION 11 A project involves components where the hardware needs minor redesig

ID: 3184804 • Letter: Q

Question

QUESTION 11 A project involves components where the hardware needs minor redesign, and has significant complexsity, software is sate of the art, and moderateby complex; and the performance depends on new system. The two hardware based weights are estimated as 0.17 each are estimated as 0.25 each. Based on this information, the value for CLF is (show your number with only two decimal places es 030 ar while the two software based weights QUESTION 12 1 points ae The earned value of a project is the O None of these are correct @ Percent of the original budget that has been earned by actual work Cost incurred minus the planned cost Project cost to date adjusted for project scope changes Total project cost to date Save QUESTION 13 Refer to the following network diagram Assuming that you have three resources, use the heurstics methoddsussed thiss ndpdoudledsotn Indicated the order in which activities are scheduled

Explanation / Answer

11) Types 2: Equal component of Hardware and software

Thus weightage for each is 0.5

CLF = 0.5 (0.17) + 0.5 (0.25) = 0.21

12) Earned value of a project is the

Percent of the original budget that has been earned by actual wok

Take the actual percentage of the completed work and multiply it by the project budget and you will get the Earned Value.

Earned Value = % of completed work X BAC (Budget at Completion)