Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Take Test: Assignment 5: du/webapps/assessment/take/launch.jsp?course assessment

ID: 3145906 • Letter: T

Question

Take Test: Assignment 5: du/webapps/assessment/take/launch.jsp?course assessment id-74531 18course_id-40398 1&conte; QUESTION CQSearch The manager of a crew at the Yokohama Tire Factory in West Point, MS oversees her employees as they mix materials to form the rubber compound that creates tires. She has t racked the crew's output over the past several weeks, obtaining these figures: Week: Crew Size: Tires Produced 250 260 125 110 What is the productivity change from weeks 5 to 62 C, 26.67% increase O 26.67% decrease 13.04% decrease O 13.04% increase QUESTION 6 figures Compute the multifactor productivity measure for each of the weeks shown for production of cowbells. What do the productivity figures Workers Material (bs) 2 4,500 4,260

Explanation / Answer

No. of cars produced per crew member from Week 5 to 6 is:

year 5 - 225/3 = 75
year 6 - 110/2 = 55

So , (55-75)/75 = -26.67%

Or the productivity has decreased by 26.67% from week 5 to week 6