A renovation of the gift shop at Orlando Amway Center has six activities (in hou
ID: 3073649 • Letter: A
Question
A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the following table, the estimates of a, m, and b times for each of the activities are listed Activity 10 28 18 14 31 18 14 18 20 19 21 16 15 19 Expected Time 14 32 18 14 Based on the activity time estimates, the expected times for each of the activities are (round your responses to two decimal places) Activity 18.67 Based on the activity time estimates, standard deviation for each of the activities is (enter your responses rounded to two decimal places). Standard Deviation ActivityExplanation / Answer
Here expected time will be calculated by
E[X] = (a + 4m + b)/6
which is calculated here
now for standard deviation
so for Activity A
SD[A] = [b -a]/6 = [18 - 10]/6 = 1.33
SD[B] = [40 - 28]/6 = 2
SD[C] = [18 - 18]/6 = 0
SD[D]= [20 - 8] /6 = 2
SD[E]= [19 - 16]/6 = 0.5
SD[F}= [21 - 15]/6 = 1
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.