Problem 1. Motorola engineers define t the center line by 6 sigma distance. The

ID: 3044528 • Letter: P

Question

Problem 1. Motorola engineers define t the center line by 6 sigma distance. The Parts Per Million (PPM) defective rate for process can be assessed to be 3.4 PPM assuming that the process can shi the center location of the process. Based on the understanding to s definition, demonstrate the de evel. [20 points] he 6-sigam process with USL and LSL locating above and below such as 6-sigma ft by 1.5 sigma distance from uch 6-sigma process capability rivation of PPM number for a process which is at 4.5 sigma capability

Explanation / Answer

4.5 sigma

P(Z > 4.5) = 3.3976*10^(-6)

= 3.4 ppm

https://www.isixsigma.com/new-to-six-sigma/dmaic/15-sigma-process-shift/

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote