A supplier for the automobile industry manufactures car and truck frames at two
ID: 3029850 • Letter: A
Question
A supplier for the automobile industry manufactures car and truck frames at two different plants. How many hours should each plant be scheduled to operate to exactly fill each of the orders in the right table? The production rates (in frames per hour) for each plant are given in the left table. All supporting work used to derive your answer(s) must be written on your paper - failure to do so will result in full credit not being given for correct answer(s). For your final answer(s), copy and complete the table below onto your paper - failure to do so will result in full credit not being given for correct answer(s).Explanation / Answer
for order 1:
let plan A operate for x hour and plant B for y hour
1066 = 5x + 8y .....eqn 1 * 2
474 = 2x + 6y .....eqn 2 *5
----------------------------
2132 = 10x + 16y
2370 = 10x + 30 y
---------------------------
14y = 238
y = 17
put this in eqn 1
1066 = 5x + 8*17
x= 186
Answer:
Number of hours of plant A = 186
Number of hours of plant B = 17
can you please solve similarly for order 2 and order 3
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.