job was timed for 60 cycles and had an average of 1.6 minutes per piece. The per
ID: 3012733 • Letter: J
Question
job was timed for 60 cycles and had an average of 1.6 minutes per piece.
The performance rating was 97 percent, and workday allowances are 17 percent.
Determine each of the following:
a.
Observed time. (Round your answer to 1 decimal place.)
Observed time
minutes
b.
Normal time. (Round your answer to 2 decimal places.)
Normal time
minutes
c.
Standard time. (Round your answer to 2 decimal places.)
Standard time
minutes
job was timed for 60 cycles and had an average of 1.6 minutes per piece.
The performance rating was 97 percent, and workday allowances are 17 percent.
Determine each of the following:
Explanation / Answer
observed time=1.6/60=0.026 min
Normal time=average element time x performance rating/100
=1.6x97/100
=1.55min
standerd time=normal time/1-allowence fraction
=1.55/1-17%
=1.87min