a) Probability that the product is defective = P(it is produced by A) * P(defective product by A) + P(it is produced by B) * P(defective product by B) + P(it is produced by C) * P(defective product by C)
=> 60/100 * 0.25/100 + 30/100 * 1/100 + 10/100 * 2/100
=> 65/10000
=> 0.0065
b) The supplier B will be the most likely to tbe source since it contributes
30/65 = 46.15% of the defective parts