43.
Question :
The contractor will least likely control costs in the following contract type:
Student Answer:
Time and materials
Firm-fixed price
Cost plus percentage of cost
Purchase order
44.
Question :
The contractor will most likely control costs in the following contract type:
Student Answer:
Cost plus percentage of cost
Time and materials
Firm-fixed price
Fixed-price incentive firm target
45.
Question :
The client is at the most risk of absorbing excessive cost overruns with the following contract type:
Student Answer:
Firm-fixed price
Time and materials
Cost plus percentage of cost
Fixed-price incentive firm target
46.
Question :
When talking face-to-face, different cultures will be at different distances from the other person, varying from a couple of feet to as close as under a foot. This area of communication can be important to cross-cultural communication and is known as:
Student Answer:
Posturing
Personal space dynamics
Linguistics
Proxemics
47.
Question :
Critical chain project management extends the critical path and adds value to project management:
Student Answer:
True
False
48.
Question :
The following factor contributes to enhanced communications for the project team communication:
Student Answer:
Smoothing over of team conflicts by the project manager
Performance appraisals
External feedback
Co-location
49.
Question :
When working in an International arena, one may encounter a cultural practice of talking about family, hobbies, weekend adventures, children before getting to the business at hand. This cultural practice is known for the following characteristic:
Student Answer:
High context
Low context
Expressiveness
Friendliness
50.
Question :
When closing out a project and looking at lessons learned, it is important to review the:
Student Answer:
WBS dictionary
Team members' resumes
Secondary risks that occurred
Checklists for risk identification
43.
Question :
The contractor will least likely control costs in the following contract type:
Student Answer:
Time and materials
Firm-fixed price
Cost plus percentage of cost
Purchase order
44.
Question :
The contractor will most likely control costs in the following contract type:
Student Answer:
Cost plus percentage of cost
Time and materials
Firm-fixed price
Fixed-price incentive firm target
45.
Question :
The client is at the most risk of absorbing excessive cost overruns with the following contract type:
Student Answer:
Firm-fixed price
Time and materials
Cost plus percentage of cost
Fixed-price incentive firm target
46.
Question :
When talking face-to-face, different cultures will be at different distances from the other person, varying from a couple of feet to as close as under a foot. This area of communication can be important to cross-cultural communication and is known as:
Student Answer:
Posturing
Personal space dynamics
Linguistics
Proxemics
47.
Question :
Critical chain project management extends the critical path and adds value to project management:
Student Answer:
True
False
48.
Question :
The following factor contributes to enhanced communications for the project team communication:
Student Answer:
Smoothing over of team conflicts by the project manager
Performance appraisals
External feedback
Co-location
49.
Question :
When working in an International arena, one may encounter a cultural practice of talking about family, hobbies, weekend adventures, children before getting to the business at hand. This cultural practice is known for the following characteristic:
Student Answer:
High context
Low context
Expressiveness
Friendliness
50.
Question :
When closing out a project and looking at lessons learned, it is important to review the:
Student Answer:
WBS dictionary
Team members' resumes
Secondary risks that occurred
Checklists for risk identification
Explanation / Answer
43.
Question :
The contractor will least likely control costs in the following contract type:
Firm-fixed price
44.
Question :
The contractor will most likely control costs in the following contract type:
Time and materials
45.
Question :
The client is at the most risk of absorbing excessive cost overruns with the following contract type:
Fixed-price incentive firm target
46.
Question :
When talking face-to-face, different cultures will be at different distances from the other person, varying from a couple of feet to as close as under a foot. This area of communication can be important to cross-cultural communication and is known as:
:
Posturing
47.
Question :
Critical chain project management extends the critical path and adds value to project management:
False
48.
Question :
The following factor contributes to enhanced communications for the project team communication:
Student Answer:
Smoothing over of team conflicts by the project manager
49.
Question :
When working in an International arena, one may encounter a cultural practice of talking about family, hobbies, weekend adventures, children before getting to the business at hand. This cultural practice is known for the following characteristic:
Student Answer:
High context
50.
Question :
When closing out a project and looking at lessons learned, it is important to review the:
Student Answer:
Team members' resumes
43.
Question :
The contractor will least likely control costs in the following contract type:
Firm-fixed price
44.
Question :
The contractor will most likely control costs in the following contract type:
Time and materials
45.
Question :
The client is at the most risk of absorbing excessive cost overruns with the following contract type:
Fixed-price incentive firm target
46.
Question :
When talking face-to-face, different cultures will be at different distances from the other person, varying from a couple of feet to as close as under a foot. This area of communication can be important to cross-cultural communication and is known as:
:
Posturing
47.
Question :
Critical chain project management extends the critical path and adds value to project management:
False
48.
Question :
The following factor contributes to enhanced communications for the project team communication:
Student Answer:
Smoothing over of team conflicts by the project manager
49.
Question :
When working in an International arena, one may encounter a cultural practice of talking about family, hobbies, weekend adventures, children before getting to the business at hand. This cultural practice is known for the following characteristic:
Student Answer:
High context
50.
Question :
When closing out a project and looking at lessons learned, it is important to review the: