43. Question : The contractor will least likely control costs in the following c

ID: 2998104 • Letter: 4

Question

43.

Question :

The contractor will least likely control costs in the following contract type:

Student Answer:

Time and materials

Firm-fixed price

Cost plus percentage of cost

Purchase order

44.

Question :

The contractor will most likely control costs in the following contract type:

Student Answer:

Cost plus percentage of cost

Time and materials

Firm-fixed price

Fixed-price incentive firm target

45.

Question :

The client is at the most risk of absorbing excessive cost overruns with the following contract type:

Student Answer:

Firm-fixed price

Time and materials

Cost plus percentage of cost

Fixed-price incentive firm target

46.

Question :

When talking face-to-face, different cultures will be at different distances from the other person, varying from a couple of feet to as close as under a foot. This area of communication can be important to cross-cultural communication and is known as:

Student Answer:

Posturing

Personal space dynamics

Linguistics

Proxemics

47.

Question :

Critical chain project management extends the critical path and adds value to project management:

Student Answer:

True

False

48.

Question :

The following factor contributes to enhanced communications for the project team communication:

Student Answer:

Smoothing over of team conflicts by the project manager

Performance appraisals

External feedback

Co-location

49.

Question :

When working in an International arena, one may encounter a cultural practice of talking about family, hobbies, weekend adventures, children before getting to the business at hand. This cultural practice is known for the following characteristic:

Student Answer:

High context

Low context

Expressiveness

Friendliness

50.

Question :

When closing out a project and looking at lessons learned, it is important to review the:

Student Answer:

WBS dictionary

Team members' resumes

Secondary risks that occurred

Checklists for risk identification

43.

Question :

The contractor will least likely control costs in the following contract type:

Student Answer:

Time and materials

Firm-fixed price

Cost plus percentage of cost

Purchase order

44.

Question :

The contractor will most likely control costs in the following contract type:

Student Answer:

Cost plus percentage of cost

Time and materials

Firm-fixed price

Fixed-price incentive firm target

45.

Question :

The client is at the most risk of absorbing excessive cost overruns with the following contract type:

Student Answer:

Firm-fixed price

Time and materials

Cost plus percentage of cost

Fixed-price incentive firm target

46.

Question :

When talking face-to-face, different cultures will be at different distances from the other person, varying from a couple of feet to as close as under a foot. This area of communication can be important to cross-cultural communication and is known as:

Student Answer:

Posturing

Personal space dynamics

Linguistics

Proxemics

47.

Question :

Critical chain project management extends the critical path and adds value to project management:

Student Answer:

True

False

48.

Question :

The following factor contributes to enhanced communications for the project team communication:

Student Answer:

Smoothing over of team conflicts by the project manager

Performance appraisals

External feedback

Co-location

49.

Question :

When working in an International arena, one may encounter a cultural practice of talking about family, hobbies, weekend adventures, children before getting to the business at hand. This cultural practice is known for the following characteristic:

Student Answer:

High context

Low context

Expressiveness

Friendliness

50.

Question :

When closing out a project and looking at lessons learned, it is important to review the:

Student Answer:

WBS dictionary

Team members' resumes

Secondary risks that occurred

Checklists for risk identification

Explanation / Answer

43.

Question :

The contractor will least likely control costs in the following contract type:

Firm-fixed price

44.

Question :

The contractor will most likely control costs in the following contract type:

Time and materials

45.

Question :

The client is at the most risk of absorbing excessive cost overruns with the following contract type:

Fixed-price incentive firm target

46.

Question :

When talking face-to-face, different cultures will be at different distances from the other person, varying from a couple of feet to as close as under a foot. This area of communication can be important to cross-cultural communication and is known as:

:

Posturing

47.

Question :

Critical chain project management extends the critical path and adds value to project management:

False

48.

Question :

The following factor contributes to enhanced communications for the project team communication:

Student Answer:

Smoothing over of team conflicts by the project manager

49.

Question :

When working in an International arena, one may encounter a cultural practice of talking about family, hobbies, weekend adventures, children before getting to the business at hand. This cultural practice is known for the following characteristic:

Student Answer:

High context

50.

Question :

When closing out a project and looking at lessons learned, it is important to review the:

Student Answer:

Team members' resumes

43.

Question :

The contractor will least likely control costs in the following contract type:

Firm-fixed price

44.

Question :

The contractor will most likely control costs in the following contract type:

Time and materials

45.

Question :

The client is at the most risk of absorbing excessive cost overruns with the following contract type:

Fixed-price incentive firm target

46.

Question :

When talking face-to-face, different cultures will be at different distances from the other person, varying from a couple of feet to as close as under a foot. This area of communication can be important to cross-cultural communication and is known as:

:

Posturing

47.

Question :

Critical chain project management extends the critical path and adds value to project management:

False

48.

Question :

The following factor contributes to enhanced communications for the project team communication:

Student Answer:

Smoothing over of team conflicts by the project manager

49.

Question :

When working in an International arena, one may encounter a cultural practice of talking about family, hobbies, weekend adventures, children before getting to the business at hand. This cultural practice is known for the following characteristic:

Student Answer:

High context

50.

Question :

When closing out a project and looking at lessons learned, it is important to review the:

Student Answer:

Team members' resumes