1. Critical activities are those that can be delayed without delaying the entire
ID: 2965303 • Letter: 1
Question
1. Critical activities are those that can be delayed without delaying the entire project
True
False
2. PERT and CPM are applicable only when there is no dependence among activities
True
False
3. a path through a project network must reach every node
True
False
4. a critical activity can be part of a noncritical path
True
False
5. the earliest finish time for the final activity is the project duration
True
False
6. Two airlines offer conveniently scheduled flights to the airport nearest your corporate headquarters. Historically, flights have been scheduled as reflected in this transition matrix.
Current
Flight
Next Flight
Airline A
Airline B
Airline A
.6
.4
Airline B
.2
.8
If your last flight was on B, what is the probability your second next flight (that is, the flight after the next flight) will be on A?
Hints: (1) what are the possible
Current
Flight
Next Flight
Airline A
Airline B
Airline A
.6
.4
Airline B
.2
.8
Explanation / Answer
1. False
An activity is said to be critical if its duration cannot be extended without delaying the completion of the project.
2. False
To apply the method, certain information is needed in advance: it must be possible to analyse the project into activities, the dependency relationships between the activities must be known, and the time taken for each activity must be known or at least estimable.
3. False
The structure of project network does not need its path to reach every node
4. True
A critical path is the sequence of scheduled activities that determines the duration of a project plan or an iteration plan. The critical path is the longest path through a project or an iteration, and determines the shortest time possible to complete the activities in the plan.
It does not determine whether the activity is critical
5. False
The earliest time is the critical path.
6.)
Possibilities are
B - A - A: Probability = .2 times .4 = .08
B - B - A : Probability = .8 times .2 = .16
Total = .08 + .16 = .24=24%