Two industrial processes are being investigated to see ifthere is a difference b
ID: 2913993 • Letter: T
Question
Two industrial processes are being investigated to see ifthere is a difference between them in producing defective items. Inprocess A, out of 8,000 items produced, 26 were defective. Inprocess B, out of 6,000 items produced, 27 were found to bedefective. Does management have any reason to suspect process B?Explain in full, and find the P-value. Two industrial processes are being investigated to see ifthere is a difference between them in producing defective items. Inprocess A, out of 8,000 items produced, 26 were defective. Inprocess B, out of 6,000 items produced, 27 were found to bedefective. Does management have any reason to suspect process B?Explain in full, and find the P-value.Explanation / Answer
Sample X N Sampleproportion
1 26 8000 0.003250
2 27 6000 0.004500
Difference = p (1) - p (2)
Estimate for difference: -0.00125
95% CI for difference: (-0.00335325, 0.000853247)
Test for difference = 0 (vs not = 0): Z = -1.16 P-Value= 0.244
hope this will helps you
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.