41) A commercial building contractor is trying to decide which of two projects t
ID: 2906778 • Letter: 4
Question
41) A commercial building contractor is trying to decide which of two projects to commit her company to. Project A will yield a profit of $50,000 with a probability of 0.6, a profit of $82,000 with a probability of 0.3, and a profit of $10,000 with a probability of 0.1. Project B will yield a profit of $100,000 with a probability of 0.1, a profit of $67,000 with a probability of 0.7, and a loss of $20,000 with a probability of 0.2. Find the expected profit for each project. Based on expected values, which project should the contractor choose? A) Project A:$55,600 B) Project A: $55,600 Project B: $52,900 Contractor should choose project A Project B: $60,900 Contractor should choose project B C) Project A: $46,600 D) Project A: $47,333 Project B: $52,900 Contractor should choose project B Project B: $49,000 Contractor should choose project AExplanation / Answer
Expected value of project A = 50,000x0.6 + 82,000x0.3 + 10,000x0.1
= $55,600
Expected value of project B = 100,000x0.1 + 67,000x0.7 - 20,000x0.2
= $52,900
Contractor should chose project A
(Option A)
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.