1) Project K costs $51,788.84, its expected cash inflows are $12,000 per year fo
ID: 2802930 • Letter: 1
Question
1) Project K costs $51,788.84, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places.
__________ %
2) A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:
The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
____________%
3) Project K costs $75,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 9%. What is the project's NPV? Round your answer to the nearest cent.
$ ____________
0 1 2 3 4Explanation / Answer
Using BA II plus calculator:
1. Go to cash flow mode
CF0= -51788.84, CF1=12000, F= 8, IRR CPT
IRR= 16.20%
IRR IS GREATER THAN WACC , ACCEPT THE PROJECT.
2. Calculation of NPVs of both projects:
Project S CF0= -1000, CF1= 882.94, CF2=240, CF3=15,CF4=10 I=8, NPV CPT= 42.556,
EAA: -42.556 PV,4 N, 8I/Y, CPT PMT, EAA= 12.85
Project L CF0= -1000,CF1=10,CF2=250,CF3=400, CF4=830.58, I=8, NPV CPT=151.62
EAA: -151.63 PV, 4N, 8I/Y, CPT PMT, EAA= 45.78
As the NPV and EAA of project L is higher , hence project Lis accepted.
IRR of project L: CF0= -1000,CF1=10,CF2=250,CF3=400, CF4=830.58, IRR CPT
IRR= 12.70%
3.CF0= -75000, CF1= 15000, F=8, I=9, NPV CPT
NPV= $8022.29 OR $8000