Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 2. When using the APV methodology, What is the NPV of the depreciation

ID: 2802553 • Letter: Q

Question

Question 2. When using the APV methodology, What is the NPV of the depreciation tax shield?

a. $32,051.52

b. $25,777.35

c. $19,165.01

d. 97,152.98

e 5-year project requires equipment that costs $80,000. If undertaken, the shareholders will contribute $20,000 cash with an interest-only loan with a maturity of 5 years and annual interest payments. The equipment will be deprecated sraight-ine t nts Save Ar and boow 560 the 5-year life of the project. There will be a pre-tax salvage value of $3,200. There are no other stant-up costs at yearDuring yeans 1 through 5, the firm will sell 20,000 units of product at s5, variable costs are $2, there are no fived costs rade-8%, r,rsity = 20%, tax rate = 30% debt-to-equity ratio-3,r,-2% OCF-80,000 ocr_. = 20,000 r(5-2) x (1-30%) + 16,000 x 30 % 46,800 OCFS = 46,800 + 3,200 = 50,000 What is the NPV of the project using the WACC methodology? $58,028 68 $89,613.03 $97,108 16

Explanation / Answer

Question 1). Answer :- Option b). $ 89,613.03

Explanation :- Calculation of Net present value (NPV) of the project :-

WACC = Weight of equity * Cost of equity + Weight of debt * Cost of debt

= (20000 / 80000) * 20 % + (60000 / 80000) * 8 % * (1 - 0.30)

= 0.25 * 20 % + 0.75 * 5.60 %

= 5 % + 4.20 %

= 9.20 %

Calculation of the free cash flow of project :-

Sales revenue (20000 * 5)

(-) Variable costs (20000 * 2)

100000

40000

Contribution margin

(-) Fixed cost

  60000

0

Earnings before depreciation, interest and tax (EBDIAT)

(-) Depreciation expense (80000 / 5)

  60000

16000

Earnings before interest and tax (EBIT)

(-) Interest expense (60000 * 8 %)

  44000

4800

Earning before tax (EBT)

(-) Tax expense (30 % of 39200)

  39200

11760

Net income

(+) Depreciation

27440

16000

Present value of cash inflows = 43440 * [ 1 - (1 + 0.092)-5 ] / 0.092 + 3200 * (1 - 0.30) / (1 + 0.092)5

= 43440 * [ 1 - (1.092)-5 ] / 0.092 + 2240 / (1.092)5

= 43440 * [ 1 - 0.644 ] / 0.092 + 2240 / 1.5528

= 43440 * 0.356 / 0.092 + 1442.56

= 168093.91 + 1442.56

= $ 169536.47 (approx).

Present value of cash outflow = $ 80,000.

Net present value (NPV) of Project = 169536.47 - 80000 = $ 89536.47 (Most nearest to the $ 89,613.03 mentioned in option b to the given question).

Conclusion :- Net present value (NPV) of Project = $ 89,613.03 (Option b).

Question 2). Answer :- Option c). $ 19165.01

Explanation :- NPV of Depreciation Tax Shield = (80000 / 5) * 0.30 * [ 1 - (1 + 0.092)-5 ] / 0.092

= 16000 * 0.30 * [ 1 - (1.092)-5 ] / 0.092

= 4800 * (1 - 0.644) / 0.092

= 4800 * 0.356 / 0.092

= 4800 * 3.86957

= $ 18573.936 (Most nearest to the $ 19165.01 mentioned in option c to the given question).

Conclusion :- NPV of Depreciation Tax Shield = $ 19165.01 (Option c)

Particulars Amount ($)

Sales revenue (20000 * 5)

(-) Variable costs (20000 * 2)

100000

40000

Contribution margin

(-) Fixed cost

  60000

0

Earnings before depreciation, interest and tax (EBDIAT)

(-) Depreciation expense (80000 / 5)

  60000

16000

Earnings before interest and tax (EBIT)

(-) Interest expense (60000 * 8 %)

  44000

4800

Earning before tax (EBT)

(-) Tax expense (30 % of 39200)

  39200

11760

Net income

(+) Depreciation

27440

16000

Free cash flow 43440
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote