Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Homework: Chapter 16 Homework Score: 0 of 1 pt Problem 16.4 Save 3 of 10 (2 comp

ID: 2797075 • Letter: H

Question

Homework: Chapter 16 Homework Score: 0 of 1 pt Problem 16.4 Save 3 of 10 (2 complete) Hw Score: 20%, 2 of 10 pts Question Help * Hartley Electronics, Inc., in Nashville, produces short runs of custom airwave scanners for the defense industry. You have been asked by the owner, Janet Hartley, to reduce inventory by introducing a kanban system. After several hours of analysis, you develop the following data for scanner connectors used in one work cell. How many kanbans do you need for this connector? Daily demand 1,200 connectors Lead time Safety stock 1.00 day Kanban size500 connectors 2 days Number of kanbans kanbans (round your response to the nearest whole number) Enter your answer in the answer box and then click Check Answer All parts showing Clear All Check Answer

Explanation / Answer

frist of all,calculate lead time demand

=lead time demand =1200*2 =2400 connectors

Safety stock = 1 day i.e1200 connectos

Reorder point = (2400+1200)/500

7.2 kanbanss or 8 kanbans