Waste Industries is evaluating a $51,300 project with the following cash flows.
ID: 2796020 • Letter: W
Question
Waste Industries is evaluating a $51,300 project with the following cash flows.
The coefficient of variation for the project is .945.
Use Appendix B for an approximate answer but calculate your final answer using the formula and financial calculator methods.
a. Select the appropriate discount rate.
b. Compute the net present value. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places.)
Explanation / Answer
a. appropraite discount rate = 16%
b.
NPV of the project = -51,300 + 9000/1.16 + 20,900/1.162 + 23,500/1.163 + 16,300/1.164 + 24,300/1.165
NPV = 7618.07
c. Accept the project