is attempting to select the best of three mutualy exclusive projects, X, Y, and
ID: 2794320 • Letter: I
Question
is attempting to select the best of three mutualy exclusive projects, X, Y, and Z. Athough all the projects have 5-year lives, they possess differing of risk Project X is in class V, the highest-risk class; project Y is in class II, the a. Find the risk-adjusted NPV for each project to the nearest cent) contents into a Project Z Project X $180 Project Y Initial investment (CFo) b. Which project, if any, would you recommend that the firm undertake? $80,000$50,000 88.000 88,000 88.000 88.000 73,000 80,000 80,000 Project Project Project 59,000 Second: Risk Classes and RADRS 13.5 5.3 19.1 Average risk Highest riskExplanation / Answer
Project X NPV
Net Present Value =16,815
Project Y Net present Value
Net Present Value =4725
Project Z Net Present Value
Net Present Value =-37092
PART - 4
Decision : Project X is Selected because highest Net Present Value.
Year Cashflow PVF @22.2 Discounted Cash Flow 0 -180000 1 -180000 1 80000 0.8183 65464 2 73000 0.6697 48888 3 60000 0.5480 32880 4 59000 0.4485 26462 5 63000 0.3670 23121Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.