A regional infrastructure building and maintenance contractor must decide to buy
ID: 2792398 • Letter: A
Question
A regional infrastructure building and maintenance contractor must decide to buy a new compact horizontal directional drilling (HDD) machine now, or wait and buy it 2 years from now when a large pipeline contract will require the new equipment. The HDD machine will include an innovative pipeloader design and a maneuverable undercarriage system. The cost of the system is $65,800 if purchased now or an estimated $80,700 if purchased 2 years from now.
At i = 12% per year and f = 5% per year, determine if the contractor should buy now or later with inflation considered.
The contractor should buy the drilling machine for $ .
Explanation / Answer
Inflation Consider Formula = i + f + if
i = interest rate ; f = inflation factor rate ; if = interest rate X inflation factor rate
i=12% ; f = 5% ;
= 12/100 + 5/100 + 12/100 X 5/100
= 0.12 + 0.05 + 0.12 X 0.05
= 0.12 + 0.05 + 0.006
= 0.176
Cost of system = $ 65,800 (purchaed now)
So Consider Cost of system (purchased now) = $ 65,800 (Present Value)
Inflation considerred = 0.176 ; No. of Years = 2 years
Future Value = P.V. X ( 1 + i )^n
P.V. = Present Value ; i = inflation consider ; n= no. of Years
P.V. = $65,800; i = 0.176; n = 2 years
= $65,800 X (1 + 0.176) ^ 2
= $65,800 X (1.176)^2
= $65,800 X 1.382
= $90,935.6
Compare this amount $ 90,935.6 with Estimated amount $ 80,700
'So Contractor should "buy Later" with inflation considered'
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.