This Question: 1 pt 31 of 50 (14 complete) TI Net present value. Quark Industrie
ID: 2782131 • Letter: T
Question
This Question: 1 pt 31 of 50 (14 complete) TI Net present value. Quark Industries has a project with the following projected cash flows: Initial cost: $260,000 Cash flow year one: $23,000 Cash flow year two: $71,000 Cash flow year three: $150,000 Cash flow year four: $150,000 a. Using a discount rate of 12% for this project and the NPV model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 17%? Should the company accept or reject it using a discount rate of 18%? a. Using a discount rate of 12%, this project should be b. Using a discount rate of 17%, this project should be , this project should be 1. (Select from the drop-down menu.) | . (Select from the drop-down menu.) I. (Select from the drop-down menu.) c. Using a discount rate of 18%. Click to select your answer(s)Explanation / Answer
a.Using a discount rate of 12% this project should be ACCPETED.
b.Using a discount rate of 17% this project should be REJECTED.
c.Using a discount rate of 18%, this project should be REJECTED.
NOTE:
a.the NPV when discount rate is 12%.
b.if 17% is the discount rate
C.iF 18% is the discount rate.
Year Cash flow Discounting factor @ 12%=(1/(1+rate)^time) Discounted cash flow1 0 260,000 1 (260,000) 1 23,000 (1/(1.12))=>0.89286 20,536 2 71,0000 (1/(1.12)^2)=>0.79719 59,596 3 150,000 (1/(1.12)^3)=>0.71178 106,767 4 150,000 (1/(1.12)^4)=>0.63552 95,328 NPV 22,227Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.