Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Och, Inc., is considering a project that will result in initial aftertax cash sa

ID: 2777202 • Letter: O

Question

Och, Inc., is considering a project that will result in initial aftertax cash savings of $1.75 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debt-equity ratio of .8, a cost of equity of 11.5 percent, and an aftertax cost of debt of 4.3 percent. The cost-saving proposal is somewhat riskier than the usual projects the firm undertakes; management uses the subjective approach and applies an adjustment factor of +3 percent to the cost of capital for such risky projects. What is the maximum initial cost the company would be willing to pay for the project?

Explanation / Answer

WACC = Cost of equity * weight of equity in capital structure + After tax cost of debt * weight of debt in capital structure

D/E = 0.8

weight of equity in capital structure = E/(D + E) = 1/(1 + 0.8) = 1/1.8

  weight of debt in capital structure = D/(D +E) = 0.8/(1+ 0.8) = 0.8/1.8

WACC = 11.5 *1/1.8 + 4.3 * 0.8/1.8

= 8.3%

  management uses the subjective approach and applies an adjustment factor of +3 percent to the cost of capital for such risky projects

There fore discount rate for project = 8.3 + 3 = 11.3%

Initial cost should be such that NPV is >= 0

NPV = Present value of cash flows - initial investment outlay

0 = initial aftertax cash savings/(discount rate - growth rate)  - initial investment outlay

initial investment outlay = 1.75/(.113 - .02)

= $ 18.8172043 m