Kerron Company is presented with the following two mutually exclusive projects.
ID: 2776176 • Letter: K
Question
Kerron Company is presented with the following two mutually exclusive projects. The required return for both projects is 18 percent. Year Project M Project N 0 –$137,000 –$368,000 1 64,800 146,000 2 82,800 193,000 3 73,800 131,000 4 59,800 123,000 Required: (a) What is the IRR for each project? (Do not round intermediate calculations. Enter your answers as a percentage rounded to 2 decimal places (e.g., 32.16).) IRR Project M % Project N % (b) What is the NPV for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) NPV Project M $ Project N $ (c) Which, if either, of the projects should the company accept?
Explanation / Answer
(a) What is the IRR for each project? (Do not round intermediate calculations. Enter your answers as a percentage rounded to 2 decimal places (e.g., 32.16).)
Project M
Using Excel Formula
IRR = irr(values)
IRR = irr({-137000,64800,82800,73800,59800})
IRR = 37.04%
Alternatively Using Equation & Trial-Run Method
At IRR PV of Cash Inflow is equal to PV of cash outflow
137000 = 64800/(1+r) + 82800/(1+r)^2 + 73800/(1+r)^3 + 59800/(1+r)^4
Solving the above equation by trial run method
IRR = 37.04%
Project N
Using Excel Formula
IRR = irr(values)
IRR = irr({-368000,146000,193000,131000,123000})
IRR = 23.37%
Alternatively Using Equation & Trial-Run Method
At IRR PV of Cash Inflow is equal to PV of cash outflow
368000 = 146000/(1+r) + 193000/(1+r)^2 + 131000/(1+r)^3 + 123000/(1+r)^4
Solving the above equation by trial run method
IRR = 23.37%
Project M 37.04%
Project N 23.37%
(b) What is the NPV for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).)
Project M
NPV = -137000 + 64800/(1+18%) + 82800/(1+18%)^2 + 73800/(1+18%)^3 + 59800/(1+18%)^4
NPV = $ 53,142.06
Project N
NPV = -368000 + 146000/(1+18%) + 193000/(1+18%)^2 + 131000/(1+18%)^3 + 123000/(1+18%)^4
NPV = $ 37511.08
Project M $ 53142.06
Project N $ 37511.08
(c) Which, if either, of the projects should the company accept?
Projects M should the company accept
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.