Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Kerron Company is presented with the following two mutually exclusive projects.

ID: 2776176 • Letter: K

Question

Kerron Company is presented with the following two mutually exclusive projects. The required return for both projects is 18 percent. Year Project M Project N 0 –$137,000 –$368,000 1 64,800 146,000 2 82,800 193,000 3 73,800 131,000 4 59,800 123,000 Required: (a) What is the IRR for each project? (Do not round intermediate calculations. Enter your answers as a percentage rounded to 2 decimal places (e.g., 32.16).) IRR Project M % Project N % (b) What is the NPV for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) NPV Project M $ Project N $ (c) Which, if either, of the projects should the company accept?

Explanation / Answer

(a) What is the IRR for each project? (Do not round intermediate calculations. Enter your answers as a percentage rounded to 2 decimal places (e.g., 32.16).)

Project M

Using Excel Formula

IRR = irr(values)

IRR = irr({-137000,64800,82800,73800,59800})

IRR = 37.04%

Alternatively Using Equation & Trial-Run Method

At IRR PV of Cash Inflow is equal to PV of cash outflow

137000 = 64800/(1+r) + 82800/(1+r)^2 + 73800/(1+r)^3 + 59800/(1+r)^4

Solving the above equation by trial run method

IRR = 37.04%

Project N

Using Excel Formula

IRR = irr(values)

IRR = irr({-368000,146000,193000,131000,123000})

IRR = 23.37%

Alternatively Using Equation & Trial-Run Method

At IRR PV of Cash Inflow is equal to PV of cash outflow

368000 = 146000/(1+r) + 193000/(1+r)^2 + 131000/(1+r)^3 + 123000/(1+r)^4

Solving the above equation by trial run method

IRR = 23.37%

Project M 37.04%

Project N 23.37%

(b) What is the NPV for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).)

Project M

NPV = -137000 + 64800/(1+18%) + 82800/(1+18%)^2 + 73800/(1+18%)^3 + 59800/(1+18%)^4

NPV = $ 53,142.06

Project N

NPV = -368000 + 146000/(1+18%) + 193000/(1+18%)^2 + 131000/(1+18%)^3 + 123000/(1+18%)^4

NPV = $ 37511.08

Project M $ 53142.06

Project N $ 37511.08

(c) Which, if either, of the projects should the company accept?

Projects M should the company accept