Mickley Company’s predetermined overhead rate is $14.00 per direct labor-hour an
ID: 2773895 • Letter: M
Question
Mickley Company’s predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-500:
What is the total manufacturing cost assigned to Job A-500?
If Job A-500 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.)
Mickley Company’s predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-500:
Explanation / Answer
Total hours for job A - 500 = Direct labor/ direct labor wage rate = 108/12 = 9 hrs
Total over head cost = overhead cost per labor hours * no. of labor hours = 14 * 9 = $ 126
total manufacturing cost = Direct materials cost + Direct labor cost + Total over head cost = 230 + 108 + 126 = $464
Cost assigned to each unit = total manufacturing cost/ number of units = 464/40 = $11.6