Listed below are twosolutions for a service issue. Work out the present costs fo
ID: 2770764 • Letter: L
Question
Listed below are twosolutions for a service issue. Work out the present costs foroption 1 for a 4 year period of time. Use a 8 % interest rateOption 1---------Option 2
First Cost-------15,000---------35,000
Maintenance--------1200yr---------900yr
Salvage-------------100------------2000
Life-------------2 years---------4 years Listed below are twosolutions for a service issue. Work out the present costs foroption 1 for a 4 year period of time. Use a 8 % interest rate
Option 1---------Option 2
First Cost-------15,000---------35,000
Maintenance--------1200yr---------900yr
Salvage-------------100------------2000
Life-------------2 years---------4 years
Explanation / Answer
Option 1 - Present cost Firstcost 15,000 + maintenance 1,200 *3.312 3,974 18,974 - salvage 2yr period 100 *0.857 86 18,888
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.