Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Breakeven cash inflows and risk Blair Gasses and Chemicals is a supplier of high

ID: 2767223 • Letter: B

Question

Breakeven cash inflows and risk Blair Gasses and Chemicals is a supplier of highly purified gases to semiconductor manufacturers. A large chip producer has asked Blair to build a new gas production facility close to an existing semiconductor plant. Once the new gas plant is in place. Blair will be the exclusive supplier for that semiconductor fabrication plant for the subsequent 5 years. Blair is considering one of two plant designs. The first is Blair's "standard" plant, which will cost $30 million to build. The second is for a "custom" plant which will cost $40 million to build. The custom plant will allow Blair to produce the highly specialized gases that are required for an emerging semiconductor manufacturing process. Blair estimates that its client will order $10 million of product per year if the traditional plant is constructed, but if the customized design is put in place. Blair expects to sell $15 million worth of product annually to its client. Blair has enough money to build either type of plant, and, in the absence of risk differences, accepts the project with the highest NPV. The cost of capital is 12%. a. Find the NPV for each project. Are the projects acceptable? b. Find the breakeven cash inflow for each project. c. The firm has estimated the probabilities of achieving various ranges of cash inflows for the two projects as shown in the following table. What is the probability that each project will achieve at least the breakeven cash inflow found in part b? d. Which project is more risky? Which project has the potentially higher NPV? Discuss the risk-return trade-offs of the two projects. e. If the firm wished to minimize losses (that is, NPV

Explanation / Answer

Year

Standard

Custom

PV

1

-30

-40

2

10

15

0.892857

3

10

15

0.797193

4

10

15

0.71178

5

10

15

0.635518

6

10

15

0.567426

Standard NPV of standard= $5,399,787.52

Custom NPV                         =$12,563,967

B . Standard breakeven= 3 years or $ 6 million per year

    Custom breakeven= 2 years 8 month or $ 8 million per year

C.

Standard $10.25 mil per year

Custom $13.325 mil per year

So yes average per year both the standard and custom plans would make plenty over the break even point.

Custom has a higher risk because the initial cost is substantially higher than the standard but the chances of return make the risk worthy. Custom also has a much higher NPV, causing it to be the natural choice for the company.

If the company is looking to minimize on losses then the standard project would be the best choices showing that the NPV doesn't drop below $0 as quickly as the Custom Project

Year

Standard

Custom

PV

1

-30

-40

2

10

15

0.892857

3

10

15

0.797193

4

10

15

0.71178

5

10

15

0.635518

6

10

15

0.567426

Standard NPV of standard= $5,399,787.52

Custom NPV                         =$12,563,967

B . Standard breakeven= 3 years or $ 6 million per year

    Custom breakeven= 2 years 8 month or $ 8 million per year

C.

Standard $10.25 mil per year

Custom $13.325 mil per year

So yes average per year both the standard and custom plans would make plenty over the break even point.

Custom has a higher risk because the initial cost is substantially higher than the standard but the chances of return make the risk worthy. Custom also has a much higher NPV, causing it to be the natural choice for the company.

If the company is looking to minimize on losses then the standard project would be the best choices showing that the NPV doesn't drop below $0 as quickly as the Custom Project

Year

Standard

Custom

PV

1

-30

-40

2

10

15

0.892857

3

10

15

0.797193

4

10

15

0.71178

5

10

15

0.635518

6

10

15

0.567426

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote