Your project is progressing well in your estimation. Your team has collected the
ID: 2754971 • Letter: Y
Question
Your project is progressing well in your estimation. Your team has collected the following data. From these data, calculate the project’s ETC.
Activity A is 60% complete at a cost so far of $50,000. It was estimated to cost $200,000 when finished. It is at the end of Week 3 of 5. Activity B is 85% complete at a cost so far of $150,000. It was estimated to cost $80,000 when finished. It is at the end of Week 4 of 5. Activity C is complete at a cost so far of $110,000. It was estimated to cost $100,000 when finished. Assume spending will continue at the same rate.
Explanation / Answer
For Activity A 60% is complete at cost of 50000
Amount required to complete remaining part = 50000*40/60 = 33333.333
For Activity B 85% is complete at cost of 150000
Amount required to complete 15% = 150000*.15/.85 = 26470.588
For Activity C is complete
Projects's estimate to complete = 33333.333+26470.588 = 59803.921
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.