Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

11. Krizum Industries makes heavy construction equipment. The standard for a par

ID: 2754956 • Letter: 1

Question

11. Krizum Industries makes heavy construction equipment. The standard for a particular crane calls for 23 direct labor-hours at $15 per direct labor-hour. During a recent period 1,450 cranes were made. The labor rate variance was zero and the labor efficiency variance was $5,400 unfavorable. How many actual direct labor-hours were worked?

38,750

33,350

33,710

31,900

12.

Munar Corporation uses activity-based costing to compute product margins. Overhead costs have already been allocated to the company's three activity cost pools-Machining, Order Filling, and Other. The costs in those activity cost pools appear below:

  Machining

$10,224

  Order Filling

$24,282

  Other

$6,900

Machining costs are assigned to products using machine-hours (MHs) and Order Filling costs are assigned to products using the number of orders. The costs in the Other activity cost pool are not assigned to products. Activity data appear below:

MHs (Machining)

Orders (Order Filling)

  Product Z3

3,300       

240       

  Product X6

10,900       

1,180       

Finally, sales and direct cost data are combined with Machining and Order Filling costs to determine product margins.

Product Z3

Product X6

  Sales (total)

$92,100        

$98,600    

  Direct materials (total)

$42,800        

$32,000    

  Direct labor (total)

$36,100        

$37,200    

What is the overhead cost assigned to Product X6 under activity-based costing? (Round the Intermediate calculation to two decimal places and your final answer to nearest whole dollar.)

$14,900

$7,848

$20,178

$28,026

13.

Brisky Corporation uses activity-based costing to compute product margins. In the first stage, the activity-based costing system allocates two overhead accounts-equipment depreciation and supervisory expense-to three activity cost pools-Machining, Order Filling, and Other-based on resource consumption. Data to perform these allocations appear below:

  Overhead costs:

  Equipment depreciation

$30,000

  Supervisory expense

$14,800  

Distribution of Resource Consumption Across Activity Cost Pools:

Activity Cost Pools

Machining

Order Filling

Other

  Equipment depreciation

0.50     

0.40        

0.10    

  Supervisory expense

0.50     

0.30        

0.20    

In the second stage, Machining costs are assigned to products using machine-hours (MHs) and Order Filling costs are assigned to products using the number of orders. The costs in the Other activity cost pool are not assigned to products.

  Activity:

MHs (Machining)

Orders (Order Filling)

  Product I3

5,530            

161             

  Product U8

17,000            

964             

  Total

22,530            

1,125             

Finally, sales and direct cost data are combined with Machining and Order Filling costs to determine product margins.

  Sales and Direct Cost Data:

Product I3

Product U8

  Sales (total)

$69,700     

$65,700     

  Direct materials (total)

$31,100     

$23,900     

  Direct labor (total)

$22,400     

$29,500     

What is the product margin for Product I3 under activity-based costing? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.)

$1,067

$8,373

$9,153

$12,933

14.

The Wright Company has a standard costing system. The following data are available for September:

  Actual quantity of direct materials purchased

30,000

pounds

  Standard price of direct materials

$5

per pound

  Material price variance

$3,000

unfavorable

  Material quantity variance

$2,000

favorable

The actual price per pound of direct materials purchased in September is: (Round your answer to 2 decimal places.)

$4.86

$5.00

$5.10

$5.14

15.

Avril Company makes collections on sales according to the following schedule:

30% in the month of sale

64% in the month following sale

6% in the second month following sale

The following sales have been are expected:

Expected Sales

  January

$100,000    

  February

$110,000    

  March

$100,000    

Budgeted cash collections in March should be budgeted to be:

$100,000

$106,400

$100,600

$100,400

11. Krizum Industries makes heavy construction equipment. The standard for a particular crane calls for 23 direct labor-hours at $15 per direct labor-hour. During a recent period 1,450 cranes were made. The labor rate variance was zero and the labor efficiency variance was $5,400 unfavorable. How many actual direct labor-hours were worked?

Explanation / Answer

Answer no. 11 :

Actual direct labour hours worked = 33710

Labour efficiency variance = - $5400

or, (SR*SH) - (SR * AH ) = - $5400

or, ( 15 * 33350 ) - ( 15 * AH ) =- $5400

or ,15 * AH = $500250+$5400= $505650

or , AH = $505650/15 = 33710 hrs.

Where ,

Labour efficiency Variance = ( SR * SH ) - ( SR * AH)

SR = Standard rate per labour hour

SH = Standard hour of Actual Production = 23 * 1450 = 33350

AH = Actual hours worked

Answer No. 12

Overhead Cost assigned to Product X6 = 10900*0.72+ 1180 * 17.1 = $28026

Answer No.13

Note 1

Note 2

Answer no.14

Actual Price per pound of direct material purchased = $ 5.1

Material price variance = - $3000

or , (SP * AQ) - (AP * AQ) = - $3000

or ( 5 * 30000) - ( AP * 30000) = - $3000

or , AP * 30000 = $153000

or AP = $153000/ 30000 = $ 5.1

where

material price variance = (SP*AQ) - ( AP * AQ)

SP = Standard price per direct material per unit

AP = Actual Price per unit of purchase material

AQ = Actual quantity of material purchased

Answer NO. 15

Budgeted Cash collection in the month of march =$106400

Activity Cost Driver Number Cost per unit of Driver Machining 10224 Mahine Hours 14200 0.72 Order filling 24282 Order 1420 17.1
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Chat Now And Get Quote