Summer Tyme, Inc., is considering a new three-year expansion project that requir
ID: 2751524 • Letter: S
Question
Summer Tyme, Inc., is considering a new three-year expansion project that requires an initial fixed asset investment of $3.9 million. The fixed asset falls into the three-year MACRS class (MACRS Table) and will have a market value of $210,000 after three years. The project requires an initial investment in net working capital of $300,000. The project is estimated to generate $2,650,000 in annual sales, with costs of $840,000. The tax rate is 35 percent and the required return on the project is 12 percent. The net cash flow in Year 0,1,2,3 and the NPV?
Explanation / Answer
Answer:
A) Calculation of Initial Cash Outflow requirement for Project (at year 0)
B) Calculation of Depreciation to be charged each year (MACRS Table)
Initial Cost of Fixed Assets = $3,900,000
Life of Fixed Assets = 3 Years
Salvage Value of Fixed Assets at end of three years = $210,000
Depreciation (As per Staraight line method) = ($3,900,000 - $210,000) / 3 = $1,230,000
Depreciation Amount as per MACRS Table
MACRS method is converted into straight line method when that method provides an equal or greater deduction.
In the above table year 3 depreciation rate in MACRS table is 14.81%. The depreciation as per MACRS table comes $1,444,372 x 14.81% = $213,911 which is less than straight line depreciation $1,230,000 hence in year 3 straight line depreciation is considered..
C) Calcuation of Present Value of Cash Flows
D) Calculation of Net Present Value
PV of Cash Flow (from C) = $4,171,930
Less: PV of Cash Outflow = ($4,200,000)
Net Present Value = -$28,070
Notes:
1) Salvage Value is considered after tax at end of year 3.
2) Since at initial stage working capital is required. It is released at the end of year 3.
Particulars Amount Cost of Fixed Asset $3,900,000 Add: Working Capital Requirement $300,000 Total Cash Outflow required for Project $4,200,000Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.