Please see the answers in the box below the question, just need to know how they
ID: 2748362 • Letter: P
Question
Please see the answers in the box below the question, just need to know how they got those answers. Please be as descriptive as possible.
The product structure for the item is given The gross requirements for item A are specified for weeks 1 through 12 in the first of the following tables. in the figure below in which the lead time for each item and constituent part is specified within brackets. Question 2 Partially correct 0.67 points out of or emAthe lead time for each tema dconstituentpathefi stofthefollowingtables. Thep od Product tru ur f P Flag question LT 1] LT 11 C (1 LT2ILT 1] D I1) G (1 LT3 LT 1 H (1 E (T) LT 11 C(1E(1) LT 21 LT 1 Item A, Level 0 01 0203 04 05 06 0708 09 1011 12 0 0 0 0 00 0 1000 01 150 ross requirements. Projected on hand lanned order receipt lanned order release Item F, Level 1 01 02 03 04 05 06 07 08 09 10 11 12 ross requirements. Projected on hand lanned order receipt lanned order release Item G, Level 2 01 02 03 04 05 06 07 08 09 10 11 12 ross requirements Projected on hand Planned order receipt Planned order release At the beginning of week 1, the on hand inventory for item F is 70 units and for item G is 110 units. There are no scheduled receipts. Determine the planned order releases for item G, and then select the correct number of units for the planned order release in specified weeks:Explanation / Answer
Projected On Hand Calculation = Last Period Closing + Scheduled Receipt + Planned Receipt - Gross Requirement Net Requirement = Last Period Closing + Scheduled Receipt - Gross Requirement (If the above calculation results in negative amount, then such amount is taken as Net Requirement, else 0) Planned Receipt = If Net Requirement > 0, Planned Receipt as per Lot Size Planned Order Release = If Planned Receipt >0, Order as per Lead Time to be placed, Here 1 week before Item = A, Level = 0 LT : 1 Week Period 0 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirement 0 0 0 0 0 0 0 100 0 50 0 150 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 0 0 Net Requirements 0 0 0 0 0 0 0 100 0 50 0 150 Planned Receipts 0 0 0 0 0 0 0 100 0 50 0 150 Planned Order Release 0 0 0 0 0 0 100 0 50 0 150 0 1 unit of Item F is required for A F is required when Order Release of A Happens Lead time is one week, so order needs to be placed 1 week prior of order receipt Item = F, Level = 1 LT : 1 Week Period 0 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirement 0 0 0 0 0 0 100 0 50 0 150 0 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 0 0 Projected On Hand 70 70 70 70 70 70 70 0 0 0 0 0 0 Net Requirements 0 0 0 0 0 0 30 0 50 0 150 0 Planned Receipts 0 0 0 0 0 0 30 0 50 0 150 0 Planned Order Release 0 0 0 0 0 30 0 50 0 150 0 0 1 unit of Item G is required for F G is required when Order Release of F Happens Lead time is three weeks, so order needs to be placed 3 weeks prior of order receipt Item = G, Level = 2 LT : 3 Weeks Period 0 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirement 0 0 0 0 0 30 0 50 0 150 0 0 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 0 0 Projected On Hand 110 110 110 110 110 110 80 80 30 30 0 0 0 Net Requirements 0 0 0 0 0 0 0 0 0 120 0 0 Planned Receipts 0 0 0 0 0 0 0 0 0 120 0 0 Planned Order Release 0 0 0 0 0 0 120 0 0 0 0 0
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.