The operations manager of a body and paint shop has five cars to schedule for re
ID: 2748055 • Letter: T
Question
The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body paint work on each are as follows:
Body work
Paint
Car
(hrs)
(hrs)
A
10
2
B
5
4
C
7
5
D
3
6
E
1
7
a) Where in the optimum sequence should car A be scheduled?
A. first
B. second
C. third
D. fourth
E. fifth
b). What is the optimum sequence (first car to last)?
A. A; B; C; D; E
B. E; D; C; B; A
C. E; B; D; C; A
D. E; D; B; C; A
E. E; B; D; A; C
c) What is the idle time at the paint work center for the optimal schedule?
A. 1 hour
B. 2 hours
C. 4 hours
D. 7 hours
E. 10 hours
Body work
Paint
Car
(hrs)
(hrs)
A
10
2
B
5
4
C
7
5
D
3
6
E
1
7
Explanation / Answer
a) Where in the optimum sequence should car A be scheduled?
A. first
B. second
C. third
D. fourth
E. fifth
Answer :
E : Fifth
Activity C & A is having the same total time .But C is having less time than for body work than A So A is considered at the last.
b). What is the optimum sequence (first car to last)?
A. A; B; C; D; E
B. E; D; C; B; A
C. E; B; D; C; A
D. E; D; B; C; A
E. E; B; D; A; C
Answer :
D. E; D; B; C; A
Activity E requires less time , hen D & B
Activity C & A is having the same total time .But C is having less time than for body work than A So A is considered at the last.
c) What is the idle time at the paint work center for the optimal schedule?
A. 1 hour
B. 2 hours
C. 4 hours
D. 7 hours
E. 10 hours
Answer :
26 - 24 = 2
b ) 2 hours
Body work Paint Total Time Required for Car Car (hrs) (hrs) A 10 2 12 B 5 4 9 C 7 5 12 D 3 6 9 E 1 7 8Related Questions