MRP: Product A is made according to the bill of materials diagram shown below. T

ID: 2747382 • Letter: M

Question

MRP: Product A is made according to the bill of materials diagram shown below.  The demand for Product ‘A’ is as follows:

Problem 1 Product A is made according to the bill of materials diagram shown below. The demand for Product 'A' is as follows: Wee 10 12 Demand 300 250 150 400 300 250 100 250 for A" Product A has a lead-time of one week B(2) C(2) The table below shows additional data for the items B, C, and D Lots of 800 units each Lot size rule Lead-time Beginning inventory Scheduled receipts L4L LAL 420 50 100 in week 3 300 in week 2 Determine the planned order release for components B, Cand D

Explanation / Answer

Lot Size here is L4L which means order size will equal to Net Requirement Item = A LT : 1 Week Week 5 6 7 8 9 10 11 12 Gross Requirement 300 250 150 400 300 250 100 250 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 Net Requirements 300 250 150 400 300 250 100 250 Planned Receipts 300 250 150 400 300 250 100 250 Planned Order Release 250 150 400 300 250 100 250 0 Projected On Hand Calculation = Last Period Closing + Scheduled Receipt + Planned Receipt - Gross Requirement Net Requirement = Last Period Closing + Scheduled Receipt - Gross Requirement (If the above calculation results in negative amount, then such amount is taken as Net Requirement, else 0) Planned Receipt = If Net Requirement > 0, Planned Receipt as per Lot Size Planned Order Release = If Planned Receipt >0, Order as per Lead Time to be placed Item = B L4L LT : 2 Week Week 3 4 5 6 7 8 9 10 11 12 Gross Requirement 0 0 600 500 300 800 600 500 200 500 Scheduled Receipts 100 0 0 0 0 0 0 0 0 0 Projected On Hand 0 100 100 0 0 0 0 0 0 0 0 Net Requirements 0 0 500 500 300 800 600 500 200 500 Planned Receipts 0 0 500 500 300 800 600 500 200 500 Planned Order Release 500 500 300 800 600 500 200 500 0 0 Item = C Lot Size = 800 LT : 1 Week Week 2 3 4 5 6 7 8 9 10 11 12 Gross Requirement 0 0 0 1500 1250 750 2000 1500 1250 500 1250 Scheduled Receipts 300 0 0 0 0 0 0 0 0 0 0 Projected On Hand 420 720 720 720 20 370 420 20 120 470 770 320 Net Requirements 0 0 0 780 1230 380 1580 1480 1130 30 480 Planned Receipts 0 0 0 800 1600 800 1600 1600 1600 800 800 Planned Order Release 0 0 800 1600 800 1600 1600 1600 800 800 0 Item = D L4L LT : 2 Week Week 4 5 6 7 8 9 10 11 12 Gross Requirement 0 600 500 300 800 600 500 200 500 Scheduled Receipts 0 0 0 0 0 0 0 0 0 Projected On Hand 50 50 0 0 0 300 0 0 0 200 Net Requirements 0 550 500 300 800 300 500 200 500 Planned Receipts 0 550 500 300 1100 300 500 200 700 Planned Order Release 550 500 300 1100 300 500 200 700 0

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Chat Now And Get Quote