consider a simple process that makes two kinds of shakes: strawberry and banana.
ID: 2746948 • Letter: C
Question
consider a simple process that makes two kinds of shakes: strawberry and banana. demand for strawberry shakes is 10 gallons per hour, while demand for bana shakes is 7.5 gallons per hour. switching from one type of shake to another requires 30 minutes to clean the production equipment so that one flavor dose not distrupt the flavor of the next shake. once production begins, the process can make 30 galons per hour of either type of shake, given these parameters, please evalute a production cycle that minimizes inventory while satisfying demand.
MSP1. how much shake is produced in total over the course of one production cycle ( in galone )?
MSP2. how much strawberry shake is produced in one production cycle (in galon)?
Explanation / Answer
Demand for strawberry shakes = 10 gallons per hour
Demand for banana shakes = 7.5 gallons per hour
Maximum production capacity = 30 gallons per hour
Time taken for production equipment cleaning = 30min = 0.5 hour
Safety stock should be done for 2 hour, as there will be 2 cleaning periods (0.5hour*2) & production time for the other shake (1hour).
Safety stock for Strawberry shake = 20 gallons
Safety stock for banana shake = 15 gallons
Hence during 1 cycle, we need to order for the safety stock + demand.
The order for strawberry shake = 10+20 = 30 gallons.
The order for banana shake = 15+7.5 = 22.5 gallons
MSP1. In one production cycle, the milkshake produced is 30+22.5 = 52.5 Gallons
MSP2. Strawberry shake produced in one production cycle is 30 Gallons
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.