Rockness Recycling refurbishes rundown business students. The process uses a mov
ID: 2746432 • Letter: R
Question
Rockness Recycling refurbishes rundown business students. The process uses a moving belt, which carries each student through the five steps of the process in sequence. The five steps are as follows:
One faculty member is assigned to each of these steps. Faculty members work a 40-hour week and rotate jobs each week. Mr. Rockness has been working on a contract from General Eclectic, which requires delivery of 1,550 refurbished students per week. A representative of the human resources department has just called complaining that the company hasn’t been receiving the agreed-upon number of students. A check of finished goods inventory by Mr. Rockness reveals that there is no stock left.
Rockness Recycling refurbishes rundown business students. The process uses a moving belt, which carries each student through the five steps of the process in sequence. The five steps are as follows:
Explanation / Answer
a.
Ans -
Max Capacity = 40 hrs x 60 mins = 2400 minutes
Step 1 - minute unpack and place on belt
Time required per student = 1.6 min
Max. Output = 2400/1.6 = 1500 students per week
Step 2 - strip off bad habits
Time required per student = 1.5 min
Max. Output = 2400/1.5 = 1600 students per week
Step 3 - scrub and clean mind
Time required per student = 0.8 min
Max. Output = 2400/0.8 = 3000 students per week
Step 4 - insert modern methods
Time required per student = 1.2 min
Max. Output = 2400/1.2 = 2000 students per week
Step 5 - polish and pack
Time required per student = 0.6 min
Max. Output = 2400/0.6 = 4000 students per week
b.
Ans -
Bottleneck: Least capacity in process = STEP 1
Process cannot create > what bottleneck is, so 1500 is max capacity for process as a whole.